A 100 MW battery proposed on Tomsons Road, now in a local environmental review the developer asked the town to waive — with the Planning Board commissioning its own fire-safety consultant and a residents' petition pushing for a moratorium.
Town of Saugerties · Ulster County · Energy storage · Status: in progress — under local review, contested
KCE NY 34 is a proposed 100 MW / 400 MWh (4-hour) lithium-ion battery storage facility on an industrial-zoned parcel at 7 Tomsons Road in the Town of Saugerties. It would occupy roughly 7 to 11 acres of a ~60-acre lot — the Planning Board minutes describe about 7 acres of battery development (with 4.6 acres of tree clearing), while the developer's NYSERDA summary estimates about 11 acres — and interconnect at Central Hudson's Saugerties 69/115 kV substation (NYISO queue C24-173). The developer, Key Capture Energy of Albany, would own and operate the site through project company KCE NY 34, LLC, and holds a NYSERDA bulk-storage incentive contract with a target in-service date of December 1, 2030. (NYSERDA project summary; Saugerties Planning Board minutes, Feb 17, 2026)
Key Capture Energy filed for site-plan approval and a special-use permit — and asked the town to issue a SEQRA negative declaration — on December 8, 2025. (NYSERDA summary) At the project's first Planning Board presentation on February 17, 2026, the board treated it as a SEQRA Unlisted action, circulated a notice of intent to serve as lead agency, and took in Part 1 of the Full Environmental Assessment Form — meaning the requested negative declaration had not been granted. (Planning Board minutes) Residents had already spoken against the project at the Town Board's January 21, 2026 meeting. (Hudson Valley One)
On May 19, 2026, the Planning Board voted 7–0 to assume SEQRA lead agency and 7–0 to refer the project to the Ulster County Planning Board — but it still issued no declaration. The town planner had drafted a Full EAF Part II flagging potential impacts (open space, Central Hudson grid upgrades, emergency particulate matter, public health). (Planning Board minutes, May 19, 2026)
By June 16, 2026 the review had hardened in two ways. The board voted 7–0 to authorize the town planner and its Chairman to retain a third-party fire-safety consultant to review the project against the updated state fire code — the applicant supporting the step and accepting the cost, and asking that the firm be NYSERDA-certified. And the town planner's segmentation analysis resolved: "NPV is advising that the projects be reviewed separately under SEQR" from the adjacent Esopus Ridge solar project, the board attorney concurring. The board also polled itself and will require a site-specific dispersion analysis, identification of every tree six inches and larger, and the full noise study rather than the summary it had been given — one member noting that a study described as modeling hot weather "states it was 50 degrees when the analysis was completed." Key Capture said a site-specific emergency response plan and Hazmat submission would come in July. (Planning Board minutes, June 16, 2026)
So the environmental review is formally underway and getting more demanding, with the developer's requested negative declaration neither granted nor foreclosed. A Town Board informational session was announced for July 15, 2026, and the Planning Board met again on July 21 — neither record is published yet.
No source located records Saugerties enacting or advancing a BESS moratorium or local law, the petition's fallback demand; Supervisor Costello is reported saying the town's building department treats a BESS as an allowable use in the industrial zone. That is the absence of a recorded law rather than a positive statement that none is contemplated. (Hudson Valley One)
The developer's representatives — Kolin Loveless and project manager Paul Williamson — point to the third-party fire review the state fire code requires, a 15-minute operator response requirement, an incident rate they put at "lower than 0.05% of all BESS installed," and a closest residential area 945 feet away. (Planning Board minutes) Key Capture's project page says the batteries will be lithium-iron-phosphate (LFP). (KCE) The fact sheet promises 20–40 union construction jobs and "millions of dollars in anticipated taxes"; the NYSERDA project summary describes a PILOT and Host Community Agreement still to be negotiated. (KCE fact sheet; NYSERDA summary)
Opposition is organized around the "Stop the Tomsons Road BESS Project" petition, launched February 4, 2026, which had 800 signatures toward a 1,000 goal by late July 2026. It asks the boards to "deny any and all applications for the Tomsons Road BESS," to "refuse to approve any large-scale BESS facilities in Saugerties" and to "amend the Town Code to prohibit BESS projects town-wide," with an immediate moratorium as the fallback. (Change.org) Residents have raised noise — "13 acres of giant electric boxes, all alive with electric hum," in one objector's words — and, in another's, that the proposal "does not specify an emergency response plan, it sidesteps a full SEQR and the direct compensation to our community is unclear." (Hudson Valley One)
a thorp party review
the project will use batteries of Lithium-Iron-Phosphate chemistry, or LFP for short,
20-40 union jobs during construction
a way to stop
Stop the Tomsons Road BESS Project
13 acres of giant electric boxes
please take it somewhere elsewhere you have plenty of open space
Saugerties is the live test of the site-specific review path while a town has no BESS-specific law on its books. The same developer is advancing a comparable project here and the question — negative declaration versus a full environmental review — mirrors what played out at the larger Terra-Gen/Alcazar site in the Town of Ulster, which the Planning Board minutes note is "more than 2x the size." The petition's fallback demand, a moratorium, is the same instrument neighboring Hurley and Plattekill used; whether Saugerties follows or instead resolves the project through SEQRA is the open question this case tracks.
These marks record whether we opened the document behind the link — not how good the source is. How we verify.