A Columbia County town that fielded developer interest but no formal application has paused battery storage twice — a 2024 chain of three short laws that ran a year and expired, then a fresh moratorium adopted in December 2025 that the board moved to extend in February 2026 — while it writes regulations.
Town of Claverack · Columbia County · Moratorium (lapsed, unconfirmed) · No in-town project
No battery storage project has been formally proposed in Claverack. The town's own law text records that it "has been approached by a developer with an interest in installing a BESS system" who argued the use was entitled to a "public utility" theory of zoning — a theory the town noted is "used to override the local home rule power." Reporting adds that two unnamed companies inquired about building storage before the town's December 2025 action. (The Daily Gazette)
Claverack has paused battery storage twice, in two separate chains. The first ran through 2024: an original three-month moratorium (Local Law 2 of 2024), a three-month extension (Local Law 4 of 2024), then a twelve-month extension (Local Law 6 of 2024) adopted with the stated intent that there be "no lapse or gap." That chain then ran out.
On December 11, 2025 the board adopted a fresh three-month moratorium — what Town Attorney Robert Fitzsimmons called "a second moratorium" — and in February 2026 scheduled a public hearing on extending the pause to six months total. Because Columbia County exempts land-use moratoria of three months or less from General Municipal Law §239-m referral, the longer term required the county planning board's review; Fitzsimmons said doing it in three-month increments was "just too much process." He also said the board might need to extend again: "It's to be determined." (The Daily Gazette)
Every Claverack instrument reaches all BESS in every district — each defines a battery storage system as essentially any rechargeable system, excluding only a stand-alone 12-volt car battery or an electric motor vehicle — not just utility-scale projects as a third-party tracker had labeled it. The written legislative intent rests on regulatory uncertainty, local control, and land use: BESS "are not uses that were contemplated within the town's comprehensive plan, or current zoning law." Fire-safety concerns appear in board discussion and reporting, but not as any law's stated purpose.
evaluate them, just like they did with solar fields, and come up with good regulations for them before they are built
Claverack shows the same precautionary posture as Livingston and Stockport — regulate before anyone builds — but with a twist the stage chain makes visible: the pause lapsed and was re-enacted rather than running continuously, and after roughly two years of moratoria the town still has no BESS regulation on the books. What the record does show is a town doing the study work it said the pause was for: engaging a consultant, drawing on NYSERDA's model law and the Pace University Land Use Law Center, and referring the question to its Comprehensive Plan Committee.
The site's confidence here is medium, and the reason is worth stating plainly. The 2024 texts are primary but are posted as undated, draft-labeled filing forms. The December 2025 moratorium rests entirely on one local newspaper report, which names no law number — and no 2025–26 BESS law appears on the town's own Codes & Laws index. Whether the six-month extension passed, and what has happened since it would have expired, is not established on the public record.